Vinyl flooring has now been fitted in the Tom Leonard gallery and break room and all landings. Carpet has been fitted in all the offices.
The folding wall has been installed, this allows the education space to be split into two classrooms or opened up into one large space for meetings and events.
Ceiling tiles have been fitted in the education space.
Door handles, locks and signs have been fitted to all the internal doors.
Electrical sockets and light fittings continue to be installed throughout the building.
Next week the fire escape stairs are installed, the lift is commissioned and the building management system will be commissioned.
Project Update - 29th July 2022
Staircase completed, exhibition room painted
Project Update - 22nd July 2022
We have windows!
Project Update - 15th July 2022
Fire escape installation, lift and BMS commissioned
Project Update - 8th July 2022
Flooring, folding wall, door fittings and electrical second fix