Externally, the fire escape staircase was completed together with the handrails to the access ramps.
Internally, the exhibition space has been spray painted dark blue. Boarding is completed around the windows. The final coat of paint is being applied throughout.
Installation of the handrails to the main staircase has been started.
In other work, a new raised floor has been installed in the Scirocco fan building to level the floor from the new building to the existing floor level, improving access. A new roof has been fitted to the "tally cabin".
Project Update - 29th July 2022
Staircase completed, exhibition room painted
Project Update - 22nd July 2022
We have windows!
Project Update - 15th July 2022
Fire escape installation, lift and BMS commissioned
Project Update - 8th July 2022
Flooring, folding wall, door fittings and electrical second fix