This website requires JavaScript.
  • Toggle Colour Mode
  • Get in touch
  • Toggle main menu
  • Toggle main menu

This week the main development has been with the ground floor underfloor heating, where the pipework has been laid ready for the concrete to be poured next week.

The roofs are nearing completion and should be finished next week.

Second-floor boarding is largely complete.

The air source heating fans are in position ready to be installed next week.

A new roof has been installed covering the entrance from the exhibition space to the mine tunnel tour.

No drone photos this week due to the drone "pilot" being on holiday.