The western face of the main roof is now complete and the southern face is nearing completion. Work has also just started on the object store roof.
Indoors, the screed has been laid on the second-floor underfloor heating.
The electrical fit-out has also progressed well - cables everywhere!
"Dot and dab" boarding has been started in the Tom Leonard Gallery.
There will be no drone photos next week as the drone "pilot" is away on holiday.
Project Update - 12th August 2022
Official handover of the building
Project Update - 5th August 2022
Finishing touches added ready for handover
Project Update - 29th July 2022
Staircase completed, exhibition room painted
Project Update - 22nd July 2022
We have windows!