Externally, the bricklayers were back for a few days to build the walls around the access ramps to the fire exits.

Internally the “dot and dab” boarding continued with the first and second floors now mainly completed. Delivery of the windows is delaying this being finished.

Electrical works continue with the (huge) main distribution panels now installed in the retail area.

Some internal doors have been fitted.

Next week, internal painting begins and the access ramps will be poured. Also, fingers crossed, the main entrance doors will be delivered.