A new concrete floor has been poured in the existing museum building.
The bridge which connected the museum to the mine tunnels has been demolished. A new bridge will replace it at the end of the mine experience.
The drainage is now complete
Project Update - 12th August 2022
Official handover of the building
Project Update - 5th August 2022
Finishing touches added ready for handover
Project Update - 29th July 2022
Staircase completed, exhibition room painted
Project Update - 22nd July 2022
We have windows!