This week has seen the ground floor concrete poured. This will "cure" for 3 weeks before it is polished to provide the final finish.
The roof is now almost complete.
Most of the second-floor partitioning is now complete.
Electrical and mechanical first fixes are nearing completion. Two of the 3 air-source heat pumps have been installed.
The scaffolding has started to be removed, revealing the final appearance of the new building.
Next week the external doors will be fitted, the remaining scaffolding will be taken down and the flagpole fitted!
Project Update - 12th August 2022
Official handover of the building
Project Update - 5th August 2022
Finishing touches added ready for handover
Project Update - 29th July 2022
Staircase completed, exhibition room painted
Project Update - 22nd July 2022
We have windows!