This website requires JavaScript.
  • Toggle Colour Mode
  • Get in touch
  • Toggle main menu
  • Toggle main menu

This week has seen the ground floor concrete poured. This will "cure" for 3 weeks before it is polished to provide the final finish.

The roof is now almost complete.

Most of the second-floor partitioning is now complete.

Electrical and mechanical first fixes are nearing completion. Two of the 3 air-source heat pumps have been installed.

The scaffolding has started to be removed, revealing the final appearance of the new building.

Next week the external doors will be fitted, the remaining scaffolding will be taken down and the flagpole fitted!