This website requires JavaScript.
  • Toggle Colour Mode
  • Get in touch
  • Toggle main menu
  • Toggle main menu

External works this week comprised of the final concrete pour for the access ramps at the back and side of the new building.

Internally all areas have now been boarded except those near the lift shaft which cannot be completed until after the lift installation next week.

The decoration is continuing throughout with most areas now having had a first coat of paint.

Washbasins have been fitted in the toilets.

Toward the end of the week, the concrete floor polishers started work on polishing the floors on the ground floor reception area. This removes a layer of the concrete to expose the gravel in the mix and provide a hard-wearing surface.

Next week the lift is being installed, glazing for the entrance doors fitted and concrete floor polishing continues.