This website requires JavaScript.

Externally, the glazing for the entrance windows has been installed, together with glazing on the dormer linking the new and original second floors.

Internally the lift has been installed but could not be commissioned as the wrong electricity meter was sent out!

Polishing of the concrete floors on the ground floors has continued with the whole floor now given its initial polish and lacquer. This will be finished next week when the lacquer is buffed.

Boarding has continued now that the lift has been installed. Most areas have now had one or two coats of paint.

Next week the floor polishing will be completed and a start made on the vinyl flooring. Decorating and electrical fitting will also continue.